Calculateur de Béton
Combien de mètres cubes et de sacs il vous faut : dalles, semelles, poteaux et escaliers
Volume, bags and ready-mix loads - add as many sections as your pour has
Dernière mise à jour: septembre 7, 2026
Getting the Volume Right
Concrete is sold in cubic yards, poured in cubic feet, and bought in bags rated by weight. Three different units for the same substance is where most ordering mistakes start.
1 cubic yard
= 27 cubic feet, and weighs about 4,050 lb — just over two tons. This is the unit ready-mix is quoted and delivered in.
Bag yields
An 80 lb bag makes 0.60 cu ft, 60 lb makes 0.45, 40 lb makes 0.30. One cubic yard is about 45 bags of 80 lb.
A ready-mix truck
Carries roughly 8 to 10 cubic yards. Below about one yard you will usually pay a short-load fee on top.
The calculator does all three conversions at once, so you can compare "45 bags to mix by hand" against "one short load delivered" before deciding.
Why We Round Bag Counts Up
Take Quikrete's own example: a 10ft by 6ft slab at 4 inches thick. That is 10 × 6 × ⅓ = 20 cubic feet. Divide by the 0.60 cu ft an 80 lb bag yields and you get 33.33 bags.
Supplier calculators typically round that to 33. But 33 bags yield 19.8 cubic feet — you would be a fifth of a cubic foot short. This calculator says 34.
The reason is not pedantry. If you run out partway through a pour, the concrete already placed begins to set before the rest arrives, and the boundary between them becomes a cold joint: a permanent plane of weakness that cracks first and lets water in. It cannot be fixed afterwards without cutting the slab out.
So expect our bag count to be one higher than a supplier's tool. That is the intent, not a discrepancy. A spare bag costs a few dollars; a cold joint costs the slab.
The Shapes, and How Each Is Measured
Slab and footing
Length × width × thickness. Enter length and width in feet but thickness in inches, because that is how slabs are specified — nobody asks for a 0.333-foot slab. A footing is the same arithmetic; it is listed separately only because you will usually want both in one job.
Round slab and round column
π × radius² × depth. Enter the diameter, not the radius — measuring across a circle is easy, finding its centre is not. Sonotube columns are the common case here, and the tube's stated size is its diameter.
Stairs
Each step is a block as wide as the stair, as deep as the run, and as tall as all the steps beneath it stacked up. Summing that gives width × run × rise × n(n+1)/2. Four steps therefore take ten step-blocks of concrete, not four — which is why stairs consume far more than people expect.
How Thick, and Why It Matters So Much
Thickness scales cost almost linearly, so it is worth choosing deliberately rather than by habit:
- 4 inches — patios, shed bases, footpaths, garden slabs. The usual residential minimum.
- 5–6 inches — driveways and anything a car sits on.
- 6 inches and up — RVs, trucks, workshop floors with machinery.
Going from 4 to 6 inches is 50% more concrete. On a 20ft × 20ft driveway that is the difference between about 5 and 7.4 cubic yards — a whole extra short load. Footing depth is a different question again, governed by local frost depth and building code rather than by load.
What Is Not in This Number
The figure above is concrete volume and what it weighs. A real pour also needs:
- Sub-base — compacted gravel, typically 4 inches under a slab
- Forms — timber, stakes and bracing, plus the labour to set them true
- Reinforcement — rebar or mesh, plus chairs to hold it at mid-depth
- Delivery and access — short-load fees, and pumping if the truck cannot reach
- Finishing — screeding, floating, edging, jointing and curing, which is skilled and time-critical work
On a typical residential slab these frequently total more than the concrete itself. Treat the material cost here as one line in the budget, not the budget.
Comment nous calculons cela
- Méthode
- Volume by shape, converted to bags and cubic yards
- Formule
-
Slab/footing = L x W x thickness. Round slab = pi x (d/2)^2 x thickness. Column = pi x (d/2)^2 x height. Stairs = width x run x rise x n(n+1)/2, since each step sits on those beneath it. Everything is computed in cubic feet, then cubic yards = cu ft / 27, cubic metres = cu ft x 0.0283168466, weight = cu ft x 150 lb. Bags = ceil(cu ft / bag yield). - Source
- Bag yields are the published Quikrete and Sakrete figures: 80 lb yields 0.60 cu ft, 60 lb yields 0.45, 40 lb yields 0.30. Density of 150 lb per cubic foot is the standard figure for normal-weight concrete, giving about 4,050 lb per cubic yard.
- Limites
- Bag counts are rounded UP on purpose. A 10ft x 6ft x 4in slab is 20 cu ft, or 33.33 bags of 80 lb; supplier calculators round to nearest and quote 33, but 33 bags yield only 19.8 cu ft and running short mid-pour leaves a cold joint - a permanent weak seam. Expect our count to be one higher than a supplier tool. Excluded entirely: forms, rebar or mesh, sub-base gravel, delivery, short-load fees, pumping, finishing and labour, which on a residential slab often cost more than the concrete. Weight assumes normal-weight concrete; lightweight mixes differ.
- Dernière vérification
Vous avez repéré un écart ? Signalez-le et nous le vérifierons ; les corrections sont publiées sur cette page. Signaler un problème